Harbour : A harbour  is a place providing safety or shelter, or a protected area in the water for anchoring boats, Its a place where ships and boats can shelter. 


Source Google

Sea Port : A sea port is a maritime facility that can comprise one or more wharves where ships can dock to load and discharge cargo and passengers. Although  frequently located on a sea coast or estuary, some ports can be situated miles inland, with access to the sea via river or canal.


Source Google
    If a port is located on a lake, river, or canal that goes to a sea or ocean, that port can be defined an inland port. Ports can also be called a harbour or harbor   

Difference between harbor and port :

A port is place on a waterway with facilities for loading and unloading SHIPS

A harbor is usually (but not always) more of a natural feature, like a bay, where ships tie up, but it is not principally for taking on cargo.

Harbours are small, used only for local or leisure use. On the other hand, a port might be the commercial part of a larger harbor.




REQUIREMENTS OF GOOD PORT :-

      1. It should have easy connections with rail and highway.
      2.  It should be situated at a place where hinterland is fertile with good population density.
      3.  Ports should have proper anchor facility, while waiting for a berth to load or unload of cargo.
      4.  Port should have adequate facilities for handling and storage of commodities.
      5.  Ports must have facilities for servicing of ships.

Ports in India :


               India has a total 13 major ports and 200 notified minor and intermediate ports. Ports play vital role in the overall economic development. About 95 per cent by volume and 70 per cent by value of the India’s international trade is carried on through maritime transport

DIFFERENCE BETWEEN MAJOR AND MINOR PORTS :

India currently has 13 Major ports and 200 notified minor and intermediate ports. There is no strict association of the traffic volume with these terms. For example, the Mundra port of Gujarat is a minor port, but it has registered a traffic volume much larger than some of the major ports.  The classification of Indian ports into major, minor and intermediate has administrative significance. The maritime transport falls under the “concurrent list” of the constitution and thus is to be administered by both the Central and the State governments.

So, while the Union Shipping Ministry administers the major ports, the minor and intermediate ports are administered by the relevant departments or ministries in the nine coastal states viz. West Bengal, Orissa, Andhra Pradesh, Tamil Nadu, Kerala, Karnataka, Goa, Maharashtra and Gujarat. Many of the 200 minor and intermediate ports are merely “notified”; little or no cargo handling actually takes place there.



Investigation and collection of data :


Investigation and collection of data necessary for the planning, design and construction of marine structures of ports and harbours after selection of a suitable site for the port.



The information required for the planning and design and construction of marine structures :

a) Survey
b) Meteorological data
c) Oceanographic data 
d) Geological data 
e) Soil investigation ,
f) Seismic data and
g) Local resources



a)Survey:Topographical survey of adequate area covered by the project is the first requirement and should be obtained at the earliest. Survey maps of ‘scale 1:50000 and contour interval of 20 m are required for general planning The recommended scales for survey maps for detailed planning
are 1:5000, 1:2500 and 1:1250 with contour interval of one metre. In no case shall the survey maps for detailed planning be of scale less than 1 I 5 000 with contour interval of one metre , depending however on topography of the area.
LIDAR 


b)Hydrographic: survey charts for the coastal region extending to continental shelf ( up to the line at which the depth of water is 200 m ) and of scale 1 : 50 000 or 1 : 25 000 ( whichever is available ) are required for general, planning. Hydrographic charts required for detailed pIanning  shall be drawn PO a scale as large as possible but in no case shall be less than 1 5 000. Recommended scales are 1 : 2 500 and 1 : 1250.



Typical Hydrographic survey





b) Meteorological data to be collected should cover the following:

l) Winds,
ll) Cyclones,
lll) Rainfall,
lv) Relative humidity,
v) Temperature, and
vl) Barometric pressures


l)Winds-For preliminary studies, information may be obtained from the available meteorological records of the area. Recording of velocity and direction of wind at the proposed site shall be obtained by installing continuous and self-recording anemometers. The data shall be collected for at least a period of one year and shall also be correlated with the data available at places nearest to the site. From the data so collected wind roses should be prepared for each month.

Typical Wind Rose Diagram for wind forces @ near site area




ll) Cyclones:- Information should be compiled regarding track of cyclones. The velocity of maximum winds, radius of maximum wind velocity, duration, pressure drop at ‘the cyclone centre and speed of movement of cyclone centre is required. From this a design cyclone is adopted and waves that could, be incident at a place computed.




Typical Metorological survey Equipment.



Information given in  Handbook of cyclonic storms ,  Tracks of storms and depressions
in the Bay of Bengal and Arabian Sea - 1964, and Synoptic charts , issued by the India Meteorological Department.



Rainfall - Data on rainfall as available should be collected from Indian Meteorological Department for a minimum period of 3 years as follows:

a) Annual aveqge rainfall,
b) Months in-which the maximum rainfall occurs,
c) Maximum intensity of rainfall and duration, and
d) Average number of wet days in a year.


Relative Humidity - Data on the maximum, mean and minimum relative humidity for every month shall be obtained for a minimum period of five years.

Temperature - The normal ambient air temperatures with emphasis on daiIy and seasonal variation may be noted.

Barometric Pressures - Data should be collected for the Data on monthly average barometric pressures nearest site from the India Meteorological Department


OCEANOGRAPHIC DATA:-

Oceanographic data to be collected should cover the following:
a. Tides,
b. Waves (wind waves and swells ),
c. storm surges,
d. Currents,
e. Salinity,
f) Sea water temperature,
d Suspended Ioad, and
h) Sea bed.


Tides -
Record of the tidal information, over as long a period as possible from Port Authorities or Geodetic and Research Branch, Survey of India or Hydrographic Department of the Indian Navy, including any local information specific to the site of the works should be obtained. Based on this the data as given in



EFFECTS OF ICE ON PORT OPERATIONS :-

                       The restraints imposed on port operations by the ice conditions during the winter season dictate more stringent and demanding design considerations than would normally be required for just seasonal operation. Depending on the local condition of the harbor and the ice regimen, the problems experienced can be due to one or all of the following:


1. The accelerated buildup of ice on the dock structure due to tidal action.
2. The interaction of the dock structure with ice driven by environmental forces.
3. The buildup of an ice "active zone" in front of the dock due to tidal action.
4. The accelerated buildup of ice in the berthing area from repeated passages of vessels due to the freezing of water that is repeatedly exposed to the atmosphere.
5. The ice buildup on the dock faces both vertical and horizontal due to wind or wave generated icings.
6. The ice-caused abrasion of structural members in the tidal zone




                                                                                 Document reference Grogery.P PHD Hand book of Ports and Harbour Engineering